+632 288 0713
+632 288 4087
MIESCOR - HANDLING OF ONE (1) UNIT 109 MT TRANSFORMER FOR BWPC WINDFARM

Project Date: October 1 – 7, 2022
G7 handled transport of One (1) Unit Transformer Main Body weighing 109 MT, from Cargo receiving to foreign vessel, roll-on to barge, sea transport Manila to Caparispisan, Pagudpud Ilocos Norte, transport/pass thru from Caparispisan / Ayoyo Trail to Caunayan Middle Ridge to Foundation the (Challenge of the project) then unloading of transformer via Manual Jacking/skidding at site's foundation.
Cargo Dimension :
One (1) Unit Transfomer (Body)
L- 8.1 x W- 3.28 x H- 4.09 = 109 MT
L- 8.1 x W- 3.28 x H- 4.09 = 109 MT
Transport Challenge :
1st Weather Condition
2ND most critical part: Passing thru Ayoyo Ridge and Caunayan Middle Ridge, it requires more tractor/prime mover to ensure safe transport
2ND most critical part: Passing thru Ayoyo Ridge and Caunayan Middle Ridge, it requires more tractor/prime mover to ensure safe transport
Transport Methodology :
Transport by: 2 x 4 Axle lines MAT with Dropdeck Trailer

SEA TRANSPORT

TRANSPORT FROM CAPARISPISAN JETTY TO SITE

UNLOADING/SPOTTING VIA MANUAL JACKING/SKIDDING
HAULING/ TRANSPORT










UNLOADING SPOTTING