+632 288 0713
+632 288 4087
MIESCOR BUILDERS INC. - HANDLING OF ONE (1) UNIT 56 MT ABB TRANSFORMER

Project Date: March 10-16, 2022
G7 handled transport of One (1) Unit Transformer Main Body weighing 65 MT, loading via Manual Jacking/skidding from Meralco Calumpit Substation to Meralco Ilo-ilo Substation
Cargo Dimension :
One (1) Unit Transfomer (Body)
L- 6.5m x 2.83m x 3.7m Weighing 65 MT
L- 6.5m x 2.83m x 3.7m Weighing 65 MT
Scope of work:
- Mobilization to Meralco Calumpit
- Loading to trailer of transformer via manual jacking/skidding
- Transport roll on to suitable LCT/Barge, seafastening
- Roll off transport to Jobsite
- Unloading/spotting to foundation via manual jacking/skidding
Transport Methodology :
Transport by: 6 Axle lines MAT

LOADING TO TRAILER VIA MANUAL JACKING/SKIDDING

TRANSPORT FROM CALUMPIT, BULACAN TO ILO-ILO

UNLOADING/SPOTTING VIA MANUAL JACKING/SKIDDING