GE ALSTOM – HANDLING OF SEVEN (7) UNITS TRANSFORMER

Picture for news item GE ALSTOM – HANDLING OF SEVEN (7) UNITS TRANSFORMER
Project Date: Oct. 2018 – January 25, 2019

G7 handled transport of Seven (7) Units OOG transformer Main Body weighing 148 MT, from Harbour Centre to NGCP Hermosa, Bataan.

Cargo Dimension :
7 Units Transformer Main Body L-6.770m W- 4.61m H-4.30m
9 Units Shunt Reactor
24 Units of SOC’s
60 Pallet Drums
Project Challenge :
Transport Height: 4.67m
Transport Width: 4.61m
Transport Methodology:
Received by: 8 Axle lines MAT
Transport by: 2 x 7 Axle lines MAT w/ Dropdeck

Transport Challenge: Bocaue Fly-Over

Transport to Final Site

Unloading/Spotting to Foundation