BENLINE AGENCIES PHIL. INC. - HANDLING OF ONE (1) UNIT 173 MT ABB TRANSFORMER

Picture for news item BENLINE AGENCIES PHIL. INC. - HANDLING OF ONE (1) UNIT 173 MT ABB TRANSFORMER
Project Date: Nov. 10-16, 2021

G7 handled transport of One (1) Unit Transformer Main Body weighing 173 MT, Shipside cargo receiving from Harbour Centre Barging to Mauban, Quezon Power Plant.

Cargo Dimension :
One (1) Unit ABB Transfomer (Body)
L- 7.80 x W- 3.76 x H- 4.84 = 173 MT
Scope of work:
  • Shipside cargo receiveing
  • Barging to Mauban, Quezon Power Plant
  • Roll-off transport to foundation area
  • Unload via Manual Jacking Skidding
Transport Methodology :
Received and Transport by: 14 Axle lines MAT

SHIPSIDE CARGO RECEIVING OF 247MT ABB TRANSFORMER

ROLL-OFF TO PAGBILAO PLANT JETTY, TRANSPORT TO PROPOSED LAYDOWN AREA

UNLOADING VIA MANUAL JACKING